Buyer guide
The RFQ checklist: ten things to prepare before asking for a price
Most delays in this trade are not negotiating delays. They are the two weeks spent asking the buyer what the can diameter is. Prepare these ten items once and every supplier can quote against them.
The ten items
| Item | What to send | Why it is asked |
|---|---|---|
| 1. Can | Diameter, total height, material (tinplate or aluminium), neck size | Sets the container range and every changeover part |
| 2. Product | What is inside, viscosity or foam behaviour, fill volume per can | Sets the filling head type and wetted materials |
| 3. Propellant | LPG, DME, compressed gas such as nitrogen, or butane; working pressure | Sets the gassing head class and the explosion-protection scope |
| 4. Output | Cans per shift, hours per shift, shifts per day, days per month | Converts to cans per minute, which sets the head count |
| 5. Existing equipment | Which of the nine stations you already own | Stops us quoting a whole line when you need one unit |
| 6. Site | Room length, width and clear height; floor loading; door width | Decides whether the line runs straight, L-shaped or in two rows |
| 7. Utilities | Voltage and phase, compressed air pressure and consumption available, water supply and drain | Anything short of the line requirement becomes a cost you find out late |
| 8. Valve, actuator, cap | Specification and current supplier of each | The feeding tooling is built to these parts, not to a standard |
| 9. Samples | Cans, valves and product for the run-up test | A machine is accepted on your components, not on ours |
| 10. Destination | Country, nearest port, preferred Incoterm | Decides packing, freight basis and which certificates travel with the crate |
What comes back
- A station list in line order, with a model number against each unit.
- A layout drawing at your room dimensions, if item 6 was supplied.
- The utility schedule: air, power and water at the connection point.
- Commercial terms and the exclusions, written out rather than implied.
The two items that delay most projects
In practice it is almost always item 6 and item 7. A buyer orders the line, then discovers the workshop door is narrower than the widest station, or that the available air supply is half what the gassing station needs. Both are cheap to check now and expensive to fix later.