The RFQ checklist: ten things to prepare before asking for a price

Most delays in this trade are not negotiating delays. They are the two weeks spent asking the buyer what the can diameter is. Prepare these ten items once and every supplier can quote against them.

01

The ten items

ItemWhat to sendWhy it is asked
1. CanDiameter, total height, material (tinplate or aluminium), neck sizeSets the container range and every changeover part
2. ProductWhat is inside, viscosity or foam behaviour, fill volume per canSets the filling head type and wetted materials
3. PropellantLPG, DME, compressed gas such as nitrogen, or butane; working pressureSets the gassing head class and the explosion-protection scope
4. OutputCans per shift, hours per shift, shifts per day, days per monthConverts to cans per minute, which sets the head count
5. Existing equipmentWhich of the nine stations you already ownStops us quoting a whole line when you need one unit
6. SiteRoom length, width and clear height; floor loading; door widthDecides whether the line runs straight, L-shaped or in two rows
7. UtilitiesVoltage and phase, compressed air pressure and consumption available, water supply and drainAnything short of the line requirement becomes a cost you find out late
8. Valve, actuator, capSpecification and current supplier of eachThe feeding tooling is built to these parts, not to a standard
9. SamplesCans, valves and product for the run-up testA machine is accepted on your components, not on ours
10. DestinationCountry, nearest port, preferred IncotermDecides packing, freight basis and which certificates travel with the crate
02

What comes back

  • A station list in line order, with a model number against each unit.
  • A layout drawing at your room dimensions, if item 6 was supplied.
  • The utility schedule: air, power and water at the connection point.
  • Commercial terms and the exclusions, written out rather than implied.
03

The two items that delay most projects

In practice it is almost always item 6 and item 7. A buyer orders the line, then discovers the workshop door is narrower than the widest station, or that the available air supply is half what the gassing station needs. Both are cheap to check now and expensive to fix later.